Enelflex
Paying large customers to reduce energy demand in Colombia
In Colombia's Sabana Norte agricultural region near Bogotá, rapid urban expansion pushed the grid to its limit – forcing flower farms, food processors, mining operations, and manufacturers to rely on polluting diesel backup generators. Enel launched Colombia's first distributed demand-side response initiative to change this.
The project contracts 21 industrial and commercial companies as Flexibility Service Providers who voluntarily reduce electricity demand during peak congestion in exchange for economic compensation. A Digital Energy Resource Management System (DERMS) calculates exactly how much flexibility is needed. Edge computing devices, a FLEXI App, and a Telegram Bot automate alerts, notifications, and recording of each flexibility event – replacing the need for diesel backup and keeping the grid stable.
€0M
avoided in infrastructure upgrades
0
tCO₂e avoided annually
0
MW peak load curtailed
0
signed customer agreements
“We knew we were implementing the first demand response project in Colombia. We installed and integrated new technology into the grid, coordinating across the company with clients at the center. One of the most valuable aspects was the training we received and the exchange with international teams, which broadened our knowledge.”
“EnelfleX marked a milestone by showing it is possible to actively integrate users into managing the electrical system, enabling fast and reliable responses to contingencies. This pilot demonstrates how grid flexibility can be a sustainable alternative to costly infrastructure upgrades.”